| Start 16: Sheboygan Falls Energy
Facility Cost: $150 million Construction of the
Sheboygan Falls Energy Facility began in June 2004, and the facility will be finished
in June 2005.
The facility will be leased under a long-term agreement to
Madison-based Wisconsin Power & Light, an Alliant subsidiary.
The plant
will be a 300-MW, simple cycle, natural gas-fired generating facility.
It
will employ two 150-MW combustion turbines.
According to Alliant Energy,
another turbine may be added in the future to increase the facility's generation
capability to 450 MW.
The plant will operate less than 10 percent of the
time, or a maximum of 1,795 hours a year. It is designed for peak-time usage,
which means it will typically operate during hot summer afternoons.
The
project's designer and construction manager is Burns & McDonnell, an engineering
and construction management company in Kansas City, Mo.
The Boldt Co. of
Appleton will perform the project's underground utilities and foundation work.
The foundations will hold the turbines, generators, auxiliary equipment and the
turbine building enclosure.
About 7,000 cu. yds. of concrete was poured
in a three-month schedule, and fly ash was incorporated in the ground to help
stabilize the foundations.
Delivering a Power Plant Dave
Rudolf, Boldt senior project manager, said the bulk and weight of power generation
equipment presented some delivery concerns.
"Getting some of the major,
heavy generating equipment out to the site was as issue because of road restrictions
and availability of rail sidings," he said. "With heavy loads like that,
if you don't have a rail siding, you have to get it to the site by truck and that
can be difficult."
He said that bridges along the delivery route were
reinforced to ensure they would handle the equipment weight. Wisconsin troopers
were brought in to close Highway 57 to traffic while the over-sized equipment
was en route.
The facility is located on 15 acres of a 40-acre site that
Alliant purchased from Power Ventures generation, a subsidiary of Burns &
McDonnell.
The construction is part of a plan to lessen the state's need
to buy power from out-of-state producers in times of heavy demand.
With
two other facilities already online, the Sheboygan facility will allow Wisconsin
Power & Light to meet peak demands with power generated in-state for the first
time since the mid-1990s. Return
to Top of 2005 list |