| Start 15: Community North Hospital
Expansion Cost: $170 million Construction began
in November on a project designed to double the size of the existing Community
North Hospital in Indianapolis.
The project will add a six-story hospital
tower, five-story medical office building and six-story parking garage.
The
850,000-sq.-ft. expansion will include "next generation" surgical suites
- designed to accommodate robotics and emerging imaging - microscopy, light control
and infection control technologies and specialty "mothers and babies hospital"
to the facility, reportedly creating the largest maternity unit of its kind in
the nation. Phased Schedule Phased completion
will bring a new entry area, new outpatient areas and the new garage into service
in the middle of 2006, followed later in the year by the office building, which
will connect to the existing hospital structure at each floor.
The hospital
tower and the new maternity area will open in early 2007.
Renovations
will be done on 130,000 sq. ft. of existing space as departments move to their
new homes.
International design firm RTKL Associates Inc. is the architect,
and Indianapolis-based BSA LifeStructures is providing engineering. Employee input
was included in the project's design.
Bob Crowder, senior project manager
for Louisville, Ky.-based Summit Construction, the general contractor, said that
an aggressive schedule on the six-story hospital tower is likely to present the
project's greatest concerns.
"There are a lot of different pieces
to this project that have to be fitted together," he said. "But the
tower is the centerpiece and is going to be the toughest part."
He
added that the other segments of the project would not have the schedule restraints
of the tower portion.
He said that keeping the hospital open for business
while work is going on will be a complex task.
"We have to maintain
traffic flow through portions of the hospital that are going to be demolished,"
Crowder said.
The solution was found in the creation of structural walkways
that allow people to pass safely while demolition and construction goes on above.
In addition, temporary partitions have been put in place to isolate renovations
from hospital activities.
As of mid-April, the concrete foundation was
going in and structural steel had been ordered.
Return
to Top of 2005 list |