| Robert H. Lurie Medical
Research Center Cost: $165 million The Robert H.
Lurie Medical Research Center in Chicago is being built in part to elevate the
stature of Northwestern University's Feinberg School of Medicine.
The 12-story
facility will house nine levels of laboratories, and each level will have 12 laboratories.
About 700 researchers, postdoctoral students and technicians will be housed in
the facility.
Research in many advanced areas - cancer, genetics, neurology,
infectious diseases, and nanotechnology - will be housed in the building.
The
remainder of the facility will include lecture halls, auditoriums and dining on
the first floor and mechanical equipment in the basement, second and top levels.
Sensitivity
to the surrounding campus buildings, many featuring Gothic design elements, was
important. Steel columns will be exposed, and the steel crossing the building
top will call to mind flying buttresses. Architectural precast dresses the building.
The
facility is named after the late real estate developer whose wife, Ann, a Northwestern
University trustee and principal of Lurie Investments Inc. in Chicago, make a
$40 million gift for the project. Earth Retention
Needed The facility in NU's downtown Chicago campus required a 40-ft.-deep
space below grade in part to hold animals used in medical research.
Because
of regulatory requirements, a large number of mechanical lines will feed the space,
and redundant services protect against loss in case a system goes down. If anything
happened to the animals, it could be a catastrophic loss to the researchers.
The
structure's location in the building-dense Streeterville area was a cause for
concern. Pressure from adjacent structures on the excavation walls could cause
them to move and other unintended outcomes, like settlement of adjacent streets
and-or buildings.
An earth-retention system that employed grouted steel
tiebacks was used to make the building's foundation rigid.
The replacement
or modification of utility lines around the site was done as a precaution to ensure
they would not fail in case settling did occur.
Inside, planning was done
to accommodate the large number of mechanical, electrical and plumbing systems.
Two
meetings were held every week for nine months to coordinate the project. For the
building's lower levels, the most complicated interstitial spaces were replicated
to ensure they were accessible after completion of the building and could be maintained.
Mock-ups
were fabricated for the laboratory casework to ensure the correct placement of
plumbing, conduit and drawers. Sixty-four fume hoods will provide independent
exhaust to the laboratory spaces.
Return
to Top of 2005 list |