|
Start 9 (tie): Borman Expressway
Cost: $300 million
As originally built in the 1950s, the
Borman Expressway in northwest Indiana featured two lanes
in either direction and was widened an additional lane in
each direction for a total of six in the mid 1970s.
But incredibly, the original pavement - now more than four
decades old - has remained.
A reconstruction project will remove and replace the pavement,
as well as the signage, lighting and drainage, said Greg Kicinski,
design-build project engineer with the Indiana Department
of Transportation in Indianapolis. The project will produce
a new 15-in.-thick plain concrete pavement and will widen
the expressway from three to four lanes in each direction,
with a fifth, continuous auxiliary lane, for entering and
exiting.
Lasts Until 2008
The project as a whole will extend from 2003 to 2008, but
the current work is the most challenging component of the
project, Kicinski said.
Three contracts are under way this summer.
The first is a $55.3 million contract let in August for the
3.5 mi. of expressway from Calumet Avenue to State Road 912,
which is also known as Pine Avenue. Gary-based Reith-Riley
Construction is removing and replacing pavement, retaining
walls, noise barriers and four bridge structures in work slated
to finish by winter.
The second, let in December to the Gary-based Superior Construction/E
& B Paving Joint Venture for $21.5 million, is for the
reconstruction of the Grant Street and Broadway interchanges,
expected to be complete by November.
In May, another contract for approximately $60 million was
let for work along a 5-mi. section from Route 912 to just
west of Interstate 65 that will be finished next year.
"That will get the bulk of the main line work done,"
Kicinski said.
The next major phase will be the reconstruction of the Interstate
80/I-65 interchange, budgeted at $130 million, which is expected
to start in fall 2006 and continue through 2007 into 2008.
The most challenging aspect of the current work is maintaining
three lanes in each direction as work proceeds. The segment
being handled by Reith-Riley carries about 165,000 vehicles
daily, about 40 percent of them trucks.
"Because of lack of alternate routes, we had to maintain
three lanes in each direction," Kicinski said, adding
that temporary widening of the roadway and splitting the project
into three phases has allowed those lanes to stay open. "They're
working basically 24-7 to get it done this season."
|
Key
Players
|
|
Owner:
|
Indiana Department of Transportation, Indianapolis
|
|
General Contractor/Design Consultant Team:
|
Reith-Riley Construction Co. Inc., Gary, Ind., and
American Consulting Engineers, Indianapolis
|
|
General Contractor/Design Consultant Team:
|
Superior Construction/E& B Paving Joint Venture,
Gary, Ind.
|
|
Design Consultant:
|
RQAW, Indianapolis
|
|
Design Consultant:
|
Butler, Fairman & Seufert Inc., Indianapolis
|
|
Consultant:
|
United Consulting Engineers & Architects, Indianapolis
|
Return
to Top of 2004 list
|