|
Start 7: Arrowhead-Weston Transmission Project
Cost: $420 million
The Arrowhead-Weston transmission project
is a 220-mi.-long power line between Duluth, Minn., and Wausau,
Wis.
Additional power transmission capability is needed in Wisconsin
because only four power lines come into the state, and power
demand keeps on going up. According to a study issued in 2002
by the U.S. Department of Energy, Wisconsin's transmission
system has one of the most congested interfaces in the country.
In contrast, nearby states reportedly have dozens of incoming
power lines.
The Arrowhead-Weston transmission project started in Minnesota
in the first quarter of this year and will run through mid-2008.
About half the line will go on existing transmission corridor,
and the rest along railroads, gas pipelines and highway corridors.
1,700 Steel Poles
The construction cycle begins with surveying and soil testing
and moves into negotiating easements. Construction follows
a typical pattern for the approximately 1,700 steel poles
to be raised, though variations are expected.
Concrete is poured for the foundations, and steel is received
in a staging area for partial assembly. The steel is moved
to the transmission line site and erected by crane into poles
125 to 160 ft. tall.
About 55 million lbs. of steel is expected to erected for
the project, said Ron Nichols of Waukesha, Wis.-based American
Transmission Co., the owner.
The final stage is the stringing of wire, sometimes in double
circuits.
Between 20 and 30 vehicle visits will be necessary for each
tower - or 24,000 to 36,000 trips.
Since project start in Minnesota, 24 foundations were completed,
Nichols said. Activity is expected to reach Wisconsin late
in the fourth quarter of this year.
Cleanliness is to be maintained during the course of construction
especially in agricultural areas. Boots and tires are selected
to ensure pathogens are not transmitted among farms.
The Arrowhead-Weston transmission project is on the high end
of the more than 100 individual projects being pursued by
members of the Midwest Independent Transmission System Operator
Inc., a Carmel, Ind.-based organization of 28 transmission-owning
firms and other energy companies in 15 Midwest states and
Manitoba, Canada.
Midwest ISO's board in June 2003 approved a $1.3 billion plan,
the Transmission Expansion Plan, to address improvements to
the energy grid. Individual members fund their projects.
|
Key
Players
|
|
Owner:
|
American Transmission Co., Waukesha, Wis.
|
|
General Contractor:
|
Wisconsin Public Service Corp., Green Bay, Wis.
|
|
General Contractor:
|
Minnesota Power, Duluth, Minn.
|
Return
to Top of 2004 list
|