|
Completion 17: 55 E. Erie St.
Cost: $126 million
The 55 E. Erie St. condominium in Chicago's
River North neighborhood is reportedly the second-largest
all-residential building in the United States.
Before the building could rise 59 stories, a large number
of underground obstacles were encountered.
Two levels of basement walls and slabs and 46 caissons for
the support of the 10-story American College of Surgeons building
previously on the site were discovered. A 9-ft.-dia. brick
tunnel, which was constructed 80 ft. below grade in the 1870s
as a water-supply channel, cut across the location. A storage
tank, sheeting and ballast slab were detected in a corner
of the site.
Containing all this was a clay deposit that, in sections,
was unstable and prone to cave-in.
Sealing the tunnel was done before the new caissons were drilled.
The city of Chicago requires the closing off of antiquated
passageways because of a famed mishap from the decade before.
In 1992, a breach occurred in a century-old tunnel under the
Chicago River during a construction project, flooding Loop
basements with 250 million gal. of water and resulting in
cleanup costs of $40 million.
At 55 E. Erie St., the grade-level slab of the previous building
was removed, permitting access to the 140-ft.-long, 70-ft.-wide,
27-ft.-deep basement. However, the walls and 2-ft.-thick basement
slab were saved because removing them would have required
extensive sheeting and bracing.
Twenty-seven openings were cut in the slab at locations where
caissons were to be drilled. Steel shoring towers were built
atop the slab to support 360,000 lbs. of drilling equipment.
Grout was injected under pressure to seal the tunnel. Steel
sleeves were installed 10 ft. above the tunnel, 10 ft. below
it and anywhere penetrations had been made to provide further
stiffening.
Looking Up
Issues arose above ground, too.
Transfer beams on four floors allow for shifting of the building's
load to the caissons.
The 13th floor, for instance, absorbs the weight of the floors
above because of the massive size of the 14 poured-in-place
transfer beams: 16 ft. high and 10 ft. wide.
The 11 floors of parking were post-tensioned partly for efficient
use of space. Because post-tensioning produces harder floors,
the slab thickness are less compared with those reinforced
with rebar.
Two sections make up the project, the main tower and a 12-story
annex where parking is located.
A 3-ft.-wide pour strip, or unformed space, was incorporated
into plans to account for the uneven settling between the
two sections.
The structure will have 214 residences and feature numerous
amenities and stylish architecture.
|
Key
Players
|
|
Owner:
|
55 E. Erie St. Investors LLC, Chicago
|
|
General Contractor and Concrete:
|
Walsh Construction Co., Chicago
|
|
Architect:
|
Fujikawa, Johnson & Associates Inc., Chicago
|
|
Structural Engineer:
|
Thornton-Tomasetti Engineers, Chicago
|
|
MEP Engineer:
|
Cosentini Associates Inc., Chicago
|
|
Caissons:
|
Case Foundation Co., Roselle, Ill.
|
|
Geotechnical Engineer:
|
STS Consultants Ltd., Vernon Hills, Ill.
|
|
Excavation:
|
Cioni Excavating, Waukegan, Ill.
|
|
Electrical:
|
Huen Electric Inc., Broadview, Ill.
|
|
Mechanical:
|
Midwesco Mechanical and Energy, Niles, Ill.
|
|
Plumbing:
|
R.J. O'Sullivan Inc., Chicago
|
|
Fire Protection:
|
Great Lakes Plumbing and Heating Co., Chicago
|
Return
to Top of 2004 list
|