|
Completion 12: South Lake Shore Drive Rebuild
Cost: $162 million
Several initiatives were implemented
to ensure that the impact on motorists was minimal during
the reconstruction of a 6-mi.-long stretch of South Lake Shore
Drive in Chicago.
Traffic flow was maintained during the height of construction,
which affected the thoroughfare between 22nd and 67th streets.
Approximately 24,000 vehicles a day go through the road segment's
southern reach, and the number increases to more than 110,000
vehicles on the segment's north end.
A movable barrier - sometimes referred to as a zipper wall
- that simultaneously closes a lane in one direction while
it opens a lane in the other was used between the Stevenson
Expressway and 47th Street to create a temporary reversible
lane. Because only five lanes of traffic on the mostly eight-lane
segment were open for use at any time, the system allowed
three lanes of traffic in the direction of rush hour.
The zipper wall, which during the project's start took five
days to link together with pins, was 3 mi. in length. To move
the wall, a machine picked up the precast segments on one
side, and they emerged from the other. The changeover took
approximately an hour.
Rebuild Due to Traffic
The segment was crumbling due to heavy traffic from everyday
use, recreation and tourism. Though the segment was resurfaced
in 1999, portions of the underlying roadway dated to the original
construction between 1910 and 1931.
A number of additional project goals were identified during
the planning, and enhancements were made to the drive's engineering,
pedestrian access and overall appearance.
No new lanes were added, but the drive is expected to handle
increased traffic due to improved roadway geometry.
An exit lane, for example, was built at northbound 47th Street
to improve traffic flow.
A new lane was also created to improve traffic safety between
the inbound lane from the Stevenson Expressway and 31st Street,
the only stretch that allows trucks.
Previously, traffic on the stretch, much of it headed to the
McCormick Place Convention Center, merged into mainline traffic.
Roadway composition varies by location.
The road between 22nd and 57th had been removed and replaced
with 9 in. of concrete. About 4,000 cu. yds. of concrete was
poured every day.
South of 57th Street, where Jackson Park starts, the composition
changes. The 9-in.-thick concrete base is topped with a 1.5-in.-thick
binder and 1.5-in.-thick asphalt surface.
Noise from traffic on the asphalt surface will be less in
the park where solitude is valued, and the dark surface will
also be less jarring than concrete's bright surface.
|
Key
Players
|
|
Owner and Funding Agency:
|
Illinois Department of Transportation, Springfield,
Ill.
|
|
Implementing Agency:
|
Chicago Department of Transportation
|
|
Adjacent Property Owner:
|
Chicago Park District
|
|
General Contractor:
|
Walsh/II in One/Riteway Joint Venture, Chicago
|
|
Program Manager:
|
Edwards & Kelcey, Chicago
|
|
Design Consultant:
|
Consoer Townsend Envirodyne Engineers Inc., Chicago
|
|
Design Consultant:
|
T.Y. Lin International, Chicago
|
|
Engineer:
|
Knight Infrastructure, Chicago
|
|
Engineer:
|
HNTB Engineers, Chicago
|
|
Engineer:
|
Civiltech Engineering, Itasca, Ill.
|
|
Concrete:
|
Prairie Material Sales, Bridgeview, Ill.
|
|
Electrical:
|
Hecker and Co., Wheeling, Ill.
|
|
Bridge Steel:
|
S&J Construction Co. Inc., South Holland, Ill.
|
|
Caissons:
|
Aldridge, Libertyville, Ill.
|
Return
to Top of 2004 list
|