|
Resch Center, Green Bay, Wis.
The $45 million Resch Center is a facility
in the Brown County Veterans Memorial Complex. The 285,000-sq.-ft.,
multipurpose arena is used for concerts (seating for 11,000
people) and sports (8,000 to 9,000).
The facility has a cable-suspended, steel-frame roof. The
structure reportedly requires fewer pounds per square foot
of steel. In addition, the shallow slope is said to create
smaller building volume that reduces heating and cooling costs
and improves acoustics yet does not create snow problems.
The roof trusses are composed of 560 tons of steel. At the
roof dome is a flat center hub that is 29 ft. wide, 144 ft.
long, and a network of cables and trusses connect to four
hub connections to support the roof.
A three-dimensional model of the steel structure was developed
and studied to address site constraints and study the erection
sequence.
The team developed a plan to erect the structure from within
the building. Eight 10-ft.-sq., 60-ft.-tall false work towers
provided temporary support for the center hub and trusses
until the cable connections could be completed.
Each cable was tuned one at a time. The difficult part was
once the tension on a cable was adjusted, the tension of the
other cables changed and had to be readjusted. Once the cables
were appropriately tensioned, the work towers were removed.
Has Serpentine Curtain Wall
Four different trades came together to build the serpentine
curtain wall.
The curtain wall is supported by tube steel because it is
so large. The foundations needed to be directly coordinated
with the steel fabricator who relied on the steel erector.
Once the structural steel was detailed, the curtain wall supplier
relied on the steel drawings to detail the system.
Another twist is the curtain wall rotated around four different
radius points, three inside.
The steel portion was the most demanding. The curtain wall
and glazing required an almost truly plumb surface for proper
attachment.
Monolithic Slab Poured
A large monolithic concrete slab pour was required for the
86-ft-wide, 200-ft.-long, 8-in.-thick ice hockey floor that
required 450 cu. yds. of concrete.
The focus was to pour the floor flat with minimal floor joints
to provide a quality surface for ice making.
The floor was poured in one continuous slab without expansion
or control joints.
Beginning at 6 a.m., a crew of 21 workers completed the task
by 5 p.m. using a wide-span screed-leveling machine, concrete
pumper truck with radio-controlled operator, four floor trowels
and two walk-behind trowels.
Communication was an issue. As the contract documents were
developed, more than 750 requests for information and 400
requested enhancements were addressed in the originally scheduled
time frame.
To manage this information, the team had access to a central
project management system, and progress was monitored using
Internet cameras. Regular coordination meetings and a tracking
system were used to manage information and communicate with
the team.
The jury said, "The cable system used for the roof is
fascinating. The curtain wall is simple and clean and nice
solution. This was very well done."
Return
to Best of 2003 list
|