|
Thornton Transitional Reservoir, Thornton, Ill.
The Thornton Transitional Reservoir will
provide 3.1 billion gallons in flood relief and is reportedly
the largest stormwater reservoir in the southern Chicago area.
The reservoir provides flood control along Thorn Creek and
the Little Calumet River, where flooding has caused more than
$6 million in damage, and will help improve the quality of
the watercourses in the Chicago area.
Since the reservoir is within 2 mi. of the Indiana border,
the beneficial effects will extend to the Hoosier State's
western part as well.
Structures were designed to divert Thorn Creek stormwater
to the reservoir to prevent the flow from overwhelming the
stream and the Little Calumet River.
When water rises above a predetermined level in Thorn Creek,
it flows to the reservoir through an intake structure, a 24-ft.-dia.
drop shaft and 8,000-ft.-long tunnel. After a storm, the reservoir
is dewatered via gravity through an 8-ft.-dia. dewatering
tunnel connected to an existing tunnel and the Calumet Water
Reclamation Plant for treatment and discharge into the Cal-Sag
Channel.
Calculation Techniques Used
New engineering and numerical computation techniques were
used in the project.
The main issue included the stability of the rock walls between
the West Lobe and Main Lobe and between the North Lobe and
Main Lobe. The only public land available for the tunnel was
directly beneath the Tri-State Tollway, and about 4,000 ft.
of the tollway is between the sheer vertical walls of the
two 250-ft.-deep lobes.
The key was to ensure the stability of the highway wall and
the quarry operator's haul tunnels above and below the proposed
diversion tunnel. The walls were geologically mapped and deep
rock borings were performed, resulting in two- and three-dimensional
maps. Stability was analyzed using a three-dimensional numerical
model.
This method would also be useful for highways in mountainous
terrain, subject to slop stability problems. The numerical
modeling, including block theory, can be applied to solve
problems in a variety of situations, such as blocky rock mass
for a permanent highway cut, quarry wall stability and high
wall cuts in hard rock.
Another element in the operation of the facility was the optimum
hydraulic shape of the diversion structure. A high-flow velocity
field will develop inside the diversion structure.
Typically, a solution is sought by using small-scale physical
modeling in a laboratory, a process that can be expensive
and time consuming. Time and money were saved by using a two-dimensional
computation model that allowed the team to determine the optimum
configuration of the diversion structure.
Creating Shafts, Tunnels
Drop and valve shafts were hollowed before the tunnels were
created.
About 25 ft. of soil was removed with excavators. Wood lagging
was mounted along the holes' sides to reinforce the lip and
prevent mud from falling in.
With the entrance steadied, about 225 ft. of rock was loosened
through drilling and blasting with dynamite. Muck was removed
with a bucket attached to a crane.
A 12-ft.-diameter shaft was built about 65 ft. away from the
center line of the 300-ft.-deep drop shaft to relieve air
pressure. The torrential onrush of water can cause pressure
to build rapidly unless there is a vent.
A tunnel-boring machine created the passageways. The TBM breaks
rock with disk cutters tipped with hard metal.
Scoops captured the rock, which dropped onto a conveyor leading
out of the tunnel.
The conveyor was anchored to a tunnel rib.
Because of the lesser cost, muck cars removed rock from the
dewatering tunnel. The system was similar to a train, as a
locomotive on a rail conveyed boxes filled with rock.
Joints in the form of vertical and horizontal cracks resulted
in extra precautions to prevent chunks from causing injury.
Strapping was used to protect workers, and a hood shielded
the machine.
Methods and Materials
The contractor used unique methods and materials to construct
the drop shaft and de-aeration shaft.
Rather than using conventional form work supported from the
floor slab, form work was designed and constructed that provides
a clear passage at the bottom of the drop shaft to the diversion
tunnel.
The 16-ft.-radius, semi-circular roof of the de-aeration chamber
was formed with a moveable steel arch form, which rolled on
steel beams supported by steel columns attached to the sidewalls.
The arch form was constructed of steel with support ribs and
access doors for vibrating concrete.
After each of the eight arch pours, the form was lowered by
jacks, and the weight was transferred to Hillman rollers. A
winch was used to reposition the form for the next pour.
The drop shaft was poured with a 20-ft.-high, 24-ft.-dia. steel
form. This was hoisted by four winches mounted at the surface.
A special concrete mix was designed and tested to reduce the
heat of hydration and control shrinkage. The mix was low in
cement and high in fly ash and allowed the contractor to pour
10-ft.-thick lifts every three days.
Structural elements were designed to provide the greatest possible
use in the future of the final Thornton Composite Reservoir,
which will provide 8 billion gallons of stormwater storage.
The jury said, "This is an amazing project, unbelievable
and innovative in all aspects.
The engineering modeling they did on this job was unquestionably
a breakthrough, and the model can be applied to highways in
mountainous terrains and other extreme conditions. They were
really thinking beyond the scope of this project to develop
necessary solutions."
Return
to Best of 2003 list
|