|
Station Upgrades Focus of
$530 Million Brown Line Overhaul
by Sheila Bacon
The Chicago Transit Authority's five-year Brown Line capacity
expansion project, a massive undertaking in which 18 of the
line's 19 stations are facing some sort of construction work,
is more than half complete.
|
The $529.9 million job broke ground in fall 2004 and has
a completion date of Dec. 31, 2009.
The expansion project's focus is new station construction
and renovations, although the contracts also include minor
track realignment and substation upgrades. Work ranges from
platform extensions that are performed while the stations
remain open and operational to construction of completely
new station houses that requires closures for 12 months at
a time.
The 9.1-mi-long, above-ground rail line serves the businesses
and neighborhoods of Chicago's North and Northwest side. Starting
with Kimball station to the north, it ends at the Merchandise
Mart station in downtown Chicago, where it connects with the
Chicago Loop. The line serves more than 66,000 customers each
weekday.
Ridership has increased approximately 83 percent since 1979
and 27 percent since 1998, and that's the highest rate of
growth anywhere in CTA's rail transportation system.
The neighborhoods along the Brown Line have grown over the
years with new residents and businesses, says Sheila Gregory,
general manager of public affairs for the CTA. This growth
has lead to increased ridership and demand for service along
the route. The goal of the expansion project is to alleviate
crowding, increase ridership capacity, improve passenger flow
and make each station Americans with Disabilities Act compliant.
Construction Contracts
The station work is divided into five separate construction
packages shared by two Chicago contractors-F.H. Paschen and
James McHugh Construction. While the majority of the work
involves station upgrades, some trackwork is involved at a
handful of locations.
The largest package of work-a $94.3 million contract-includes
renovated stations and new trackwork at the Belmont and Fullerton
stations. Both stations are remaining open during the work,
with only temporary closures.
FHP crews are currently erecting steel to rebuild tracks at
both stations, says Matt Moss, FHP project manager. Work includes
new caisson foundations, cast-in-place concrete columns, new
steel structure, a cast-in-place concrete deck and a cast-in-place
concrete platform. Work is phased so that the existing track
can be used while the new track is being built, Moss adds.
Crews are installing a new direct fixation track system at
both stations in which trackwork is cast into the concrete
deck instead of placed on an open-tie elevated structure,
Moss says.
Temporary stations have been built and are currently in service.
Renovation work at the existing stations will begin after
trackwork is complete in late 2008, Moss says.
Longer-term closures have been necessary at Kimball, Kedzie,
Francisco and Rockwell stations-four of the five stations
(Western is the fifth) included in FHP's $19.9 million contract.
Kedzie and Rockwell stations opened in August after six-month
closures, and Kimball opening in January. Francisco was the
latest to reopen in March.
Work at Kedzie, Francisco and Rockwell has included demolition
of existing platforms and their foundations and the installation
of new precast concrete foundations to support the new platforms.
New station houses were built at Kedzie and Rockwell, and
Francisco's historic station house was taken offsite, restored
and reinstalled.
Substantial completion of the five-station work package is
expected in August.
Work at Chicago, Armitage and Sedgwick stations-a $45.5 million
contract also being performed by FHP-is halfway complete.
The bulk of the work includes installing new foundations for
the new platform decking. Armitage and Sedgwick will also
require limited trackwork and tie replacement. The stations
remain open, with only temporary weekend closures.
About $58 million in upgrades are planned for Irving Park,
Damen, Addison and Montrose stations, which will face temporary
closures. The Addison and Montrose stations closed on in December
and will remain closed for 12 months. McHugh is the general
contractor.
Work at Addison and Montrose is in the substructure phase,
says Mike Gould, McHugh's vice president of heavy/highway
and infrastructure. Crews are excavating, removing and replacing
the existing spread footings that support the elevated structure
and placing new footings for the new station houses.
The new stations will include revamped entries and exits to
accommodate the extended platforms, and stairways and elevators
will be reworked to comply with ADA requirements, Gould says.
Once Addison and Montrose are complete in late 2007, Irving
Park and Damen will close for one year and similar work will
begin.
Preliminary survey and utility relocation work is currently
under way at Wellington, Diversey, Paulina and Southport stations.
Southport closed in April and will remain closed for one year.
Diversey will follow suit this spring. The $66.9 million contact
will include reconstruction of all four stations. Work is
being performed by FHP.
Bigger Trains, Bigger Platforms
The majority of the station reconstruction work is being done
to accommodate eight-car trains, says the CTA's Gregory. Before
the renovation work began, only six-car trains could berth
at the platforms at 16 of the 19 Brown Line stations. Throughout
the rest of the CTA's rail system, station platforms are long
enough to accommodate the longer trains.
Platforms at all the stations under construction will be extended
approximately 100 ft. to allow a one-third increase in berthing
capacity over the current six-car service. In addition to
extending the platforms, stations are being made accessible
to passengers with disabilities with the addition of either
elevators or ramps and wheelchair accessible turnstiles.
Other station improvements include wider stairways, additional
turnstiles and improved entrances and exits to allow for better
customer flow. Security cameras and brighter lights are also
being installed at the stations, along with upgraded public
address systems.
The designs of the new and renovated Brown Line stations were
shaped by the involvement of area residents and business owners,
who had been participating in community meetings regarding
the project since 2001, Gregory says. Seven teams completed
designs for stations, substations and signal and communications
components of the project.
"These designers worked together to identify common solutions
for lighting, canopy designs, various standard details, material
and finishes," Gregory says.
"This was an innovative idea that was necessary to achieve
CTA's goal of providing common design elements to all of the
stations."
Accommodating All
Work has been scheduled so that no two adjacent stations (located
no farther than half a mile from the next station) are temporarily
closed at the same time on weekdays, Gregory says. Passengers
are also encouraged to use other CTA rail lines as well as
bus service during the station closures.
Contractors are also doing their part to make sure passengers
remain safe during construction. Crews are working off-hours,
redirecting passengers to temporary stations and isolating
pathways to existing stairways and walkways from the active
worksite, FHP's Moss says.
Accommodating nearby businesses during the construction work
has been a problem in many places because entrances to shops
and restaurants are immediately beneath the suspended structure
or in the path of new construction, Gould says.
"In some places, you can't go 20 ft without being in
front of someone's door or loading dock," he adds.
Contractors take part in neighborhood task force meetings
and keep neighbors updated on construction activities well
in advance of work being performed, Gould says. Crews have
been able to accelerate certain activities and rework schedules
in order to accommodate delivery schedules and business hours
of those nearby.
Additional work includes upgrades to the Brown Line's signal
system and renovations at Clark Junction. Signals are being
upgraded from Kimball to Western, which involves installing
signal equipment along the tracks; installing six new crossing
gates and circuitry where the Brown Line crosses at street
level at Spaulding, Kedzie, Albany, Sacramento, Francisco
and Rockwell; and rehabilitating Kimball Tower where signals
control switches and direct trains.
At Clark Junction-the location where Brown, Purple and Red
Line tracks merge just north of the Belmont station-work has
been completed to install a new signal system from Armitage
to Addison, provide signals for 14 rail crossovers and rehabilitate
Clark Tower.
The Brown Line project also includes substation upgrades and
in some cases replacement. A new substation is being installed
on Grace Street, and the Clark Street substation is being
rehabilitated. Crews are also installing AC power supplies,
supervisory control, DC switchgear, indoor and outdoor lighting,
security and communications equipment at both facilities.
Work began on Jan. 10, 2005, and is expected to be completed
late this year.
The CTA will solicit bids for upgrades and replacements of
the Brown Line's communication equipment later this year.
Click here for next Feature Story >>
|