Sherman Plaza
Evanston's Tallest Condo To Offer 28 Stories of Views
by
Pamela Dittmer McKuen
The Evanston skyline is bolder and brighter
with the addition of the 28-story Sherman Plaza, a residential and retail development
capturing Lake Michigan panoramas.
|
It's a city jewel that began as simple garage renovation.
In
the 1920s, the three major retail meccas in the Chicago area were the Loop, Oak
Park and Evanston. Then came World War II and the emergence of regional shopping
malls, and shoppers followed.
Evanston, with its university and lakefront,
fared better than many suburbs, but continually looked for ways to maintain its
downtown vitality.
About a decade ago, city planners saw that the 30-year-old,
600-space public garage on Sherman Avenue needed work. Engineers said it should
be torn down and rebuilt.
That led to the question about what else should
be built. Ideas for a more comprehensive construction project flowed, and were
revised multiple times.
"With each glitch, with each change, we got
a much better project than the one that was originally proposed," said Assistant
City Manager Judith Aiello.
The $190 million project, the highest-dollar
mixed-use project in Evanston, is a joint venture between Focus Development Inc.
in Northfield and Klutznick-Fisher Development Co. in Chicago.
"Sherman
Plaza gives us a wide range of modern space needs which also allows us to build
upon our strengths," Aiello said. That and other recent construction "achieve
our goal of a 24/7 downtown."
Anchoring the project is the condominium
tower, The Residences at Sherman Plaza, which houses 253 lofts, penthouses and
apartment-style condominiums. The units, which are sold out, range in size from
900 sq. ft. to 4,000 sq. ft. and were priced between the upper $200s and $1.9
million.
The tower would have been the city's tallest building, but early
design changes took it just inches below the Chase Building. As it stands, it
is the city's tallest residential building, said Focus Project Manager Mike de
Lannoy.
The tower connects to 152,000 sq. ft. of retail space on two levels
and a 1,585-space public parking garage, creating an L-shaped footprint. All together,
Sherman Plaza encompasses nearly a city block, bordered by Church and Davis streets
and Sherman and Benson avenues and previously occupied by parking.
Seeking
Human Scale The enormity of the project, from a design standpoint, is visually
scaled to human size.
Although basically a single, poured-in-place concrete
building, the various areas of use stand at differing heights and sport differing
facades. The first six floors and the entire retail center are clad in brick.
The three penthouse floors, 23 through 25, are tiered like a wedding cake and
ribboned with high-performance, floor-to-ceiling windows. They are crowned with
a three-story mechanical penthouse. The silo-like garage elevator is encased in
glass.
OKW Architects Inc. in Chicago serves as architect of record, and
Daniel P. Coffey & Associates Ltd., also in Chicago, serves as design architect.
"Each
retail building is meant to look like a different building," said project
architect Tim Schmitt of OKW. "They have different colors and scales of brick
and different window spacings, which allow it to look like not one massive development
done at one time, but kind of integrated projects. It's very contextual."
"The
condominium and retail areas each have their own little bit of character,"
said architect Daniel Coffey. "The elevator tower is clearly understandable
as a destination."
One of the hallmarks of Focus construction is sky-high
green space, and Sherman Plaza is no exception. The building meets lot lines,
but rooftop gardens on the third, fifth and seventh floors are decked with trees,
shrubs, grass and flowers and provide nearly half an acre of outdoor respite for
condominium residents.
Had Numerous Obstructions After
years of planning, construction of Sherman Plaza began in December 2004.
There
was no basement to excavate, but the caissons required drilling about 70 ft.
Underground
were numerous and costly obstructions due to poor ground conditions and deep foundations
of previous buildings on the site. "Potholing," which is making trial
bores, helped locate obstructions near grade, but for deeper ones, crews had to
widen their holes or try harder to get through.
In one case, the rock was
impenetrable despite numerous attempts. Finally the decision was made to drill
two additional caissons about 10 ft. on either side of the rock and to lay a bridge
beam across them so that the column support could be put in as planned. That bit
of unanticipated engineering added $90,000 to the tab.
"When you put
together your budget for a building like this, you have a contingency amount and
this is some of the stuff you use that for," de Lannoy said. "You try
to avoid it but you can never avoid paying some extra."
Cost increases
for materials, including steel, copper and plastics, also pinched the budget,
although contract pricing helped, de Lannoy said.
"I think we used
about 2,500 tons of rebar total," he added. "We ordered as early as
we could, but you have to order it as you need it. You can't have steel sitting
around. It takes up too much room." Accommodating
Evanston Logistics The project had other issues as well. For one, an endeavor
of this magnitude, within a bustling urban environment, calls for careful attention
to logistics. It takes lots of planning and scheduling, de Lannoy said.
"Just
getting the trucks in - on a busy day there could be 80 trucks," he said.
"We're on three busy streets in downtown Evanston, and the city is very sensitive
to street closures. Sometimes we'd stage the trucks a couple of blocks away and
call them in on the radio as we need them."
Concrete had to be timed
precisely; if it sat in a truck too long, the load had to be rejected, de Lannoy
added.
"It all has to do with how long it takes the truck to get to
the site," he said.
Yet another headache was the high winds coming
in from Lake Michigan. On many days the winds exceeded 50 mph, causing the tower
crane to be shut down and delaying the project. By mid-spring, the schedule was
a month behind.
The initial closings on the condominium units will begin
this summer, which is later than planned, but the overall closing schedule will
be speeded up to meet the original completion date of July 2007. Click
here for next Feature >> |