Features
 Current Features
 Past Features





Feature Story - August 2005
Southern Illinois Project
Dam the Ohio River!

by Craig Barner

The epic $1.4 billion Olmsted Locks and Dam began in southern Illinois in November 1992, and this summer crews are preparing to start assembling the $564 million dam, which should be complete in 2013.

advertisement

The project on the Ohio River moved into a new stage in July 2004 when crews were mobilized to construct the dam, said Richard Schipp, resident engineer with the U.S. Army Corps of Engineers, the federal agency overseeing the project.

Tony Sandor, a project manager with Boise-based Washington Group International, a member of the Washington/Alberici Constructors Inc. Joint Venture serving as the general contractor, said the preparatory work includes the 1,000-ft.-long, 300-ft.-wide yard to be used to form the precast dam pieces, or "shells;" 1,600-ft.-long skidway with rail and rollers to transport the shells to the river edge; and work areas.

The 2,700-ft.-long dam will feature tainter gates adjacent to locks on the Illinois side, fixed weir on the Kentucky side and traditional wicket gates in the middle. In the spring, when the river level is high, barges will cruise above the submerged wicket gates without stopping.

"It's much cheaper for the industry to never have to stop, wait in line [for lock space] and then go through," added Larry Bibelhauser, Olmsted project manager for the Corps of Engineers.

When river levels are low, the dam will be used to maintain the pool for the 45 mi. between Olmsted and the Smithland Locks & Dam in Hamletsburg, Ill. In this situation, the wicket gates will be partly above water at Olmsted, and river craft will use the locks to pass.

The locks feature two 110-ft.-wide, 1,200-ft.-long chambers.

After barges enter a chamber, the miter gates close. Valves are opened to let water in the chamber and elevate the craft, or valves are opened to let water out and lower the craft, depending on whether it is going upstream or downstream.

The chamber's water level changes as the pressure equalizes. "There is no pump," Bibelhauser added. "It's all based on gravity."

When the water level is at the desired level, the miter gates at the other end of the chamber open to permit the craft to exit.

One for Two

The Olmsted project is replacing Locks and Dams No. 52 and 53 upstream. The antiquated structures, which were completed in1929, can no longer handle river traffic without significant delay.

"This dam (Olmsted) will probably have to operate about the same frequency as 52" or about 40 percent of the year, Bibelhauser said.

Nos. 52 and 53 are the last of more than 50 locks and dams from the late 19th and early 20th centuries that will have been replaced on the Ohio since the 1950s between Pittsburgh and southern Illinois.

Nos. 52 and 53 will be demolished, and the project is expected to be complete in 2014.

"This is the busiest stretch of river [in the United States] as far as tonnage goes mainly because you're in an important junction," Bibelhauser said.

About 100 million tons of cargo - coal, grain, petroleum - are carried annually on barges between Cairo, Ill., and Paducah, Ky. They can go east to Cincinnati or Pittsburgh; or west to New Orleans or St. Louis via the Mississippi River.

A federal appropriation covers half the Olmsted project cost, and the Inland Waterways Trust Fund covers the other half. The navigation industry pays a tax on diesel fuel that goes into the fund.

$600 Million Completed

Previous to the dam, about a dozen contracts valued at about $600 million were completed.

The major elements included a $65.7 million lock cofferdam, the $271.6 million lock and the $106.7 million approach walls.


Lock Cofferdam:

A temporary lock cofferdam was constructed between June 1993 and December 1995 to expose a portion of the river bottom immediately adjacent to the shore. Once the river bottom was dry, the lock was constructed.

More than 8,500 109-ft.-long sheets were driven into the river bottom with a pile-driving hammer on a barge. Laid end to end, the sheets would have stretched 171 mi.

"They were the longest sheets Bethlehem Steel had ever made," the Corps of Engineers' Schipp added.

The interlocked sheets created 51 circular cells, some 64 ft. in diameter, which formed the cofferdam's rectangular perimeter.

"Generally, you drive the sheet 5 ft. down, go to the next and drive it and go around the cell," Schipp said. "You make several passes until you get 15 to 20 ft. down into the soil."

Mud from the river bottom was dredged and pumped into the hollow cells for sturdiness.

Up to 15 barges were being used at a single time during the cofferdam project.

Lock:

The lock was constructed between December 1995 and November 2001.

Because the project lies in the New Madrid Seismic Zone, the lock needs to be secure in case of an earthquake, Bibelhauser said.

As a result, 12,000 45-ft.-long steel H-piles were driven into the ground, and rebar was set.

In March 1997, a major setback occurred when the river flooded and water poured over the cofferdam perimeter. By May, the water had receded, and about 1 ft. of mud had been deposited.

Machinery was brought in to suck up the dry mud, but the results were only so-so. In the end, hand labor was used to remove the mud.

About $15 million and six months were required for the remediation, Bibelhauser said.

The government, contractor and contractor's insurer each ponied up the money.

Once the cleaning was complete, concrete pours began, and about 700,000 cu. yds. were poured. A 12-ft.-thick slab forms the lock bottom, and three walls - land, middle and river - lie on top.

"Inside those walls is a box culvert, and that's where we let the water in and out to be able to raise and lower the barges [in the chamber]," Bibelhauser said.

When the lock was complete, the cells were removed to flood the lock.

Approach Walls:

Because the typical barge has three 35-ft.-long tows, approach walls are needed to guide the craft into the locks.

"You're trying to get the front that is a quarter-mile away while you're pushing the barge from the back [where the motor is]," Schipp said. "Those walls are important."

There are four approach walls of varying length, with the longest a third-mile long.

Because the river's height will fluctuate, the approach walls will occasionally become submerged and muddy.

As a result, floating guide walls were designed to reduce maintenance costs.

Eleven 375-ft.-long segments that make up the approach walls were built in a "graving yard" in Paducah, towed to the site, assembled in the lock chamber with bolts and set.

Four nose piers made up of three, linked 10-ft.-diameter pipes filled with concrete and steel were installed at the tip of the approach walls as protection.

"You have to have something pretty substantial out there when that big tow comes through," Bibelhauser said. "It might lose control, high water might twist him around or the wind might blow."

SIDEBAR

Designing a Dam

A hope in planning the design of the Olmsted dam was to eliminate a wicket gate-only dam.

When a wicket-gate dam needs to be open or closed, a dam tender in a boat with rod hooks the door-like wickets that shut against the dam's sill, said Larry Bibelhauser, Olmsted project manager for the U.S. Army Corps of Engineers, the federal agency overseeing the project. "It's kind of a dangerous job," he added.

The design of the 2,700-ft.-long dam calls for five-bay tainter gates near the Illinois side, traditional wicket gates in the middle and a fixed weir on the Kentucky side. The design has advantages.

The 140 wickets stretch 1,400 ft., and in high water, the gates will be submerged and allow boats to float above.

In addition, the tainter gates permit for better control of the pool. This is an advantage

in a region where hydropower generation upstream can produce a sudden rush of water downstream during peak summer electrical demand.

"The hydropower guys can open up the water, let the water go through to generate electricity and shut it off an hour later," Bibelhauser said. "That tends to screw with the guys [downstream].

"I got these [tainter] gates and don't have to worry about that. I push a button, change it (the pool) and control it better."

The concrete tainter gate shells - including stilling basin, sills and piers - will be fabricated on shore. Then they will be moved to the river edge via a skidway, set on a lifting frame and moved into the river on a catamaran barge with 5,000-ton lifting capacity.

"Think of the concrete shell piece as a shoebox that you take the lid off and turn upside down," said Richard Schipp, resident engineer with the Corps of Engineers.

The shells are lowered, and the tremie concrete that is typically used under water will be pumped under the shell, forcing out the water.

 

 

 Click here for more Features >>


 


Sponsors

© 2009 The McGraw-Hill Companies, Inc.
All Rights Reserved