Features
 Current Features
 Past Features





Feature Story - September 2004
Plan Z
Design-Build Process Expedites Work at 22 South Bend Schools
By Steve Kaelble

Want to put extra zip into a design-build project?

Work for a client who is empowered and well organized.

That's what helped Wight & Co. and its partners pull off a complex project of school renovation and expansion in South Bend, Ind.

The South Bend Community School Corp., in the midst of a reorganization of its grade-level structure, needed to accomplish significant work at a half dozen locations along with smaller tasks at more than a dozen additional schools. School officials, having a couple of years earlier experienced a building project that seemed to never end, wanted this one to proceed rapidly, with as little interruption as possible to the activities of students and teachers.

advertisement

The project was known as the Plan Z reorganization and totaled $50.8 million, said Bob Farkas, senior project manager for Wight & Co., which is based in Downers Grove, Ill., and maintains a South Bend office.

"That covers the planned capital improvements as well as renovations and additions to meet a new curriculum and a shift in the grade levels," he added.

Plan Z divided students among "primary centers" serving kindergarten through grade 4, "intermediate centers" housing grades 5-8 and traditional high schools covering grades 9-12.

"We took a series of elementary schools and made them into intermediate centers," and a high school became an intermediate center and math/science magnet academy" Farkas said. He added that the project "touched 22 different schools."

Wight's relationship with the South Bend schools began in 2000 when Superintendent Joan Raymond recommended that the company take over management of a high-school construction project that was 85 percent complete but more than a year behind schedule. Raymond had worked with Wight while serving in a job elsewhere, and she hired the company in July 2000 to take charge of the high-school project and have it ready for classes in the fall.

The company successfully accomplished that mission and was therefore considered a natural for the massive Plan Z project when the district was ready to sign a contract two years later. Wight began work on Plan Z in late summer 2002 and was called upon to deliver some of the buildings in time for fall 2003 classes and the remaining buildings by the start of classes this fall.

"Wight Construction Services handled program management," using both inside and outside architects and MEP designers, Farkas said. "We drove it from Day 1 and compressed it and accelerated it to meet the demand that Dr. Raymond set for us."

Farkas added that the biggest elements of the project were:

  • The LaSalle Intermediate Academy was once a high school and is now a math-science magnet school. Among the highlights of this building is a new "smart lab" for industrial-technology students that's filled with high-tech computer-design tools and manufacturing equipment.
  • The Kennedy Primary Academy, a 1960s-era building with a no-longer-workable design, which was gutted. "It was an open-concept building" without traditional classroom walls, just 4-ft. masonry dividers, Farkas said. "It was probably a cool idea in the 1960s, but it wasn't going to work now," he added. Wight constructed regular classrooms and support facilities.
  • The Jefferson Intermediate Center, a 75-year-old building, which Wight renovated and then constructed an addition. Farkas said the final product included an addition of about 25,000 sq. ft.
  • The Marshall Intermediate Center was created from an existing single-level school. Wight completed a 22,000-sq.-ft. addition.
  • The Greene Intermediate Center, another existing single-level school, was expanded by about 13,000 sq. ft.

    Wight also coordinated projects at a number of other school properties. Farkas said South Bend-based Forum Architects designed roofing at 12 different schools, and M/E Design Services of nearby Mishawaka designed HVAC systems in eight buildings.

    Undertaking such significant work in school buildings requires a minimum of disruption to student activities. In the schools that had additions, Wight spent the school year for the most part focusing on those additions, where classes were not being held. That left the summer months to tackle renovations in the remainder of the buildings.

    In one case, it was simply not possible to perform enough of the required work during the off months, so it was necessary to bring in portable buildings to house some of the classes during construction.

    One of the most difficult parts was conducting HVAC renovations while school was in session, Farkas said. At one school, for example, "during the winter we had to limp along on one boiler," he added. Transitioning to new systems occasionally left some classrooms too hot or too cold as adjustments were made.

    All buildings also needed to be durable. "Students are very rough on the building," Farkas said. That means the use of masonry walls, high-impact drywall and "light fixtures that can't be pulled out of the ceiling," he added.

    Among the local firms assisting Wight with the Plan Z project was DLZ Indiana LLC, an architectural engineering firm based in Ohio, with Indiana headquarters in South Bend.
    "DLZ provided site survey, mechanical, electrical and structural engineering services, and at the Kennedy Primary Center we provided architectural services," said project manager Aaron Shultz. The firm was involved at seven of the schools.

    The project required compressed design times, Shultz said. "We had about five to six months of design, for what normally would have been close to a year," he added.

    Plenty of overtime was needed, but so was close cooperation of the school corporation, which had personnel specifically dedicated to interacting with the various contractors. "I think that was probably the biggest part of the success," Shultz said.
    "We knew exactly what the owner wanted. They had really done some good planning."

    Equally important, the school corporation gave one person the authority to make key decisions about design and construction, rather than insisting that the school board have its hands in all of the decisions.

    When school boards that meet only every week or two become engaged in the details, "you lose a lot of time waiting to get approvals," Shultz added.

    And while Farkas said he has found some Indiana school officials to be skeptical of the design-build approach, he added that the scheduling challenges inherent in this kind of project make design-build an ideal choice. "It cannot be done traditionally," he said.
  •  

     Click here for more Features >>


     


    Sponsors

    © 2008 The McGraw-Hill Companies, Inc.
    All Rights Reserved