Above-Ground
Planning Augurs Calumet Tunnel's Progress
Shafts and tunnels near surface, deep in
limestone make up last leg of 'Deep Tunnel'
by Craig Barner
It took plenty of coordination among multiple entities to
get work started on the $168.7 million Little Calumet Leg,
the last passageway in Cook County's 109.4-mi.-long Deep Tunnel
system.
Utility firms moved gas and water lines because of the potential
for service disruption during the sinking of more than 50
shafts for the 7.9-mi.-long project, said Greg Hauser, project
manager for the Jay Dee/Affholder Joint Venture, the South
Holland, Ill.-based general contractor.
ComEd, a local utility, routed electrical service to the construction
shaft because energy was required for below-ground lighting
and other systems.
Union Pacific Railroad Co. allowed 2,000 ft. of its utility
road for a nearby rail line to be used to transport workers
and materials to the main construction shaft, thereby saving
cost and labor.
Multiple government agencies - the U.S. Army Corps of Engineers,
the village of South Holland, the Illinois Department of Transportation
- helped ensure proper access and siting for the Little Calumet
Leg project, the last passageway of the $3.1 billion Deep
Tunnel system that will ultimately provide pollution and flood-control
benefits for Chicago and 51 Cook County suburbs.
The Calumet project's original site configuration was a mile
long and 300 ft. wide due in part to adjacent wetlands, Hauser
said. A wider space was preferable so equipment could be staged
near the construction shaft and the substantial amount of
rock removed from tunneling could be easily piled.
"Now, we got a wider [site]" that's not as long
but easier to work in, Hauser added.
Several nearby towns, such as South Holland, Calumet City
and Dolton, organized community meetings so the blasting and
mining process could be explained and residents' concerns
allayed, Hanson said.
Explosive emulsion, rather than dynamite, was used to open
the drop shafts. The emulsion, which is less sensitive than
dynamite, is safer.
"The nitroglycerin fumes from dynamite are not toxic,
but they give you a heck of a headache," Hauser said.
"We don't have those fumes here."
Fathoming the Tunnel
The tunnel will provide pollution control and overflow abatement
for all or parts of eight south suburban communities. It runs
in a southeast-to-northwest direction between the Indiana
line and Interstate 57.
The tunnel will provide relief for the Little Calumet River,
which was previously inundated with overflows from combined
sanitary and storm sewers during heavy rains. The project
will prevent 2 billion gal. of combined raw sewage and 1.5
million lbs. of polluting organic material from being discharged
into the waterway each year, according to projections from
the Metropolitan Water Reclamation District of Greater Chicago.
The project started in February 2002 and is expected to be
complete by March 2006.
Soil, Rock Tunnels in Design
A large number of tunnels and shafts in the soft ground near
the surface and deep in the limestone rock comprise the design
of the Little Calumet Leg tunnel.
Connecting shafts in the soft ground intersect the combined
sewer system at many points to channel effluent into exit
tunnels, said Jim Foley, project engineer with the Jay Dee/Affholder
Joint Venture. About half of the more than 47 soft-ground
shafts are already complete.
Sensors will monitor water levels in the exit tunnels, and
regulating structures will open sluice gates when levels are
high. About 5 mi. of exit tunnels between 42 in. and 120 in.
in diameter and 15 regulating chambers will channel runoff
into drop shafts, which range between 7 ft., 2 in. and 30
ft. in diameter.
"At each of the 10 drop shafts, we're picking up at least
one and in most cases, [two to six] system sewers," Hauser
added.
Effluent is dropped more than 100 ft. into a chamber, which
was formed by drilling and explosives.
Air pressure due to the onrush of water was accounted for
in the design, Hauser said. Three drop shafts are next to
sister shafts that allow air to rush out.
The others have a divided wall of precast concrete, Foley
said. Water spills into one side, and air shoots up the other.
Notches were put in the shaft walls when they were formed,
and precast panels were inserted, Foley added.
Each shaft is equipped with a louver that allows air to be
vented during rain while preventing noxious vapors in the
tunnel from escaping during dry weather, he said.
The main tunnel has a slope so gravity can be used to channel
effluent, Foley said. It runs down-hill from the tunnel ends,
which are 160 ft. deep, to the middle, which is 210 ft. deep.
A connecting passageway will link the Calumet tunnel with
the previously constructed, 30-ft.-diameter Indiana Avenue
tunnel, which is 313 ft. below ground, Hauser said. It channels
sewage to a treatment plant at 130th Street.
"If the whole tunnel system is full, then it will still
have to overflow into the Little Calumet River, but that will
be after the initial flows have gone into the Deep Tunnel,"
Hauser said. "That will be much cleaner."
Tricky Tunnel Logistics
Project logistics are complex.
Because it is 300 ft. long, the tunnel-boring machine for
the limestone tunnel came in components and needed careful
assembly, Foley said. The pieces were staged above ground,
and a crane lowered them into the passageway. Once down, each
piece was moved slightly forward so room was available for
the succeeding piece immediately after.
The assembled machine consists of several components, such
as the cutting wheel and trailing gear, said Jim Davis, engineer
with the Jay Dee/Affholder Joint Venture.
Teeth form the leading edge, and the cutting wheel turns to
slice rock.
TBMs for soft-ground use created the tunnels for the near-surface
areas.
Another logistical issue involved removing the debris cut
away during mining, Hauser said. A continuous conveyor in
the limestone tunnel removes debris as it is cut, and additional
conveyor bracket is installed as the TBM moves along.
The conveyor terminates at the main shaft, where a vertical
conveyor takes over. A system of buckets brings the debris
to the surface, where it is piled.
In the soft-ground tunnels, trains on rails removed the debris.
Moving formwork and concrete was important because each structure
is to be lined with concrete. Platforms were used to suspend
workers from cranes, the formwork and rebar were installed
and the concrete was pumped in.
Because of the depth and length of the Calumet tunnel, a different
method of installation was used to line it. The concrete is
pumped into the tunnel in large quantities and put into cars
with agitators. They are rolled, the forms are installed and
the concrete is pumped.
Unlike the shafts, the tunnels are not reinforced with rebar.
"The lining is not structural," Hauser said. "It's
for infiltration and exfiltration, to keep the sewage in and
the groundwater out."
Approximately 7,000 to 8,000 cu. yds. of concrete is presently
being pumped a month, and the peak is expected next summer
at 15,000 cu. yds. a month, Hauser said.
"Right not we've only finished nine structures in concrete,"
he added.
|
Plumbing
the Deep Tunnel
The first phase of the $3.1 billion Deep Tunnel project,
also known as the Tunnel and Reservoir Plan, is nearly
done, and it will consist of 109.4 mi. of tunnels, more
than 250 drop shafts and 600 surface-connecting and
flow-control structures.
The construction of the nearly complete 8.1-mi.-long
Torrence Avenue Leg and the 7.9-mi.-long Little Calumet
Leg tunnels will shift the focus of the project.
Three reservoirs to hold 15.7 billion gal. of water
will become the project spotlight, according to the
Metropolitan Water Reclamation District of Greater Chicago.
The smallest basin, the O'Hare Reservoir, is complete
and will hold 350 million gal. of water. A temporary
reservoir in south suburban Thornton is done and will
hold 3.1 billion gal. of water for 14 years while the
permanent one is mined for a capacity of 7.9 billion
gal. The largest reservoir in the project is planned
for southwest suburban McCook.
When fully implemented, the project is expected to provide
pollution and flood-control benefits for Chicago and
51 Cook County suburbs. Completion is expected in the
2010s.
|
|