New
Year, New Pavement
Stone matrix asphalt used creatively on $80
million Interstate 57 project
by Jeffrey Steele
When workers resurfaced the southbound lanes of Interstate
57 last summer, they discovered that the stone matrix asphalt
they put down on the road had unusual characteristics.
"We found the SMA didn't want to adhere to the polished
concrete [existing road surface]," said Dirk Fuqua, engineer
of project implementation for the Illinois Department of Transportation
District One in Schaumburg. "It did eventually, but when
it was hot, it was kind of moving around on us, and we didn't
like that."
As a result, when it came time to resurface the northbound
lanes this summer, the team working on the project added 0.75
in. of a 4.75-millimeter sand mix on top of the polished concrete,
then topped it with 1.75 in. of SMA binder and another 1.75
in. of SMA surface.
The resulting new pavement is 4.25 in. thick, and its three
layers all have different purposes, Fuqua said. The sand mix
acts as a buffer between the polished concrete and the SMA.
The binder is regular stone aggregate, while the surface is
a steel slag aggregate.
"We put the steel down for friction characteristics;
it provides better protection against skidding and accidents,"
Fuqua added. "SMA itself is a mix. It's rock on rock.
It's got larger stone in there. In a normal bituminous mix,
the stone and sand are bound together with the asphalt.
"In an SMA, the rock is fairly large, and the rock rests
on top of the rocks. So it's a really solid layer for us.
We're using that in all our expressway resurfacing."
12 Mi. of Resurfacing
The project involves patching and resurfacing a 12-mi. length
of I-57 from Halsted Street south of the Bishop Ford Expressway
down to Interstate 80, as well as rebuilding bridge decks
between 119th and 159th streets. This summer's work is budgeted
at $43 million.
The total project is worth $80 million and is slated for completion
by Oct. 31. Lemont, Ill.-based K-Five Construction Corp. is
the general contractor.
This is the first resurfacing for I-57, a roadway whose original
construction dates back more than a quarter century. Prior
to the work, I-57 was in "decent shape," but a number
of cracks had begun appearing and the road was in the early
stages of erosion, Fuqua said.
"We needed to go in and patch and surface before the
road turned to gravel on us," he added.
Robert DeFrancesco, superintendent with Lemont, Ill.-based
K-Five, said patching consisted of removing existing pavement
and laying down new concrete.
"The holes weren't deep," DeFrancesco said. "It
was just deteriorated concrete. It was bad concrete that had
to be removed and replaced. There was a lot of patching."
Special attention is given to stretches of roadway leading
up to bridges because they contain a lug system that helps
prevent some traffic pressure from impacting the bridges.
To replace the lug system, contractors first remove the "continuously
reinforced concrete" near the bridges, DeFrancesco said.
After removing that pavement, the area is excavated, then
12 in. of aggregate stone are placed in the bed, topped by
4 in. of asphalt base. Forms are then set, reinforced steel
laid down and 13 in. of concrete poured to create the roadway.
Safety of Workers
As it does on all road projects, IDOT is working to ensure
safety for workers. Because stage construction is used, traffic
is being reduced from three to two lanes through the work
zone. All workers are behind a barrier wall or barricades,
Fuqua said.
DeFrancesco said that "safety is a big thing with the
state of Illinois." He said extra signage and a multitude
of flaggers are helping ensure safety for both the workers
and the motoring public.
"When we first started, we had weekly meetings, and now
it's pushed back to every two weeks," he added. "At
those meetings, we hit on safety, traffic control, everything.
And that involved the state of Illinois, the general contractor
and all [eight] subcontractors."
Fuqua said there has only been one serious blemish to a good
safety record. "A motorist got behind the barrier somehow
and hit one of the workers who was doing pavement striping,"
he added. "He was not a state employee, but with one
of the contractors."
DeFrancesco said the worker was killed. "We'd completely
closed off lanes where the [motorist] had no business at all,"
he said. "The guy just came into the closure and hit
him."
Bridge-Deck Work
Fuqua said workers are on the project from approximately sunrise
to sundown, but if the schedule demands it, longer hours may
have to be put in later this summer.
Had the project involved only resurfacing, the work probably
could have been finished at night, "but we have those
bridge decks, so we can't have just nighttime closures and
still be able to pour and cure concrete," he added.
Filled with potholes and in "bad shape," the decks
had become a chore for IDOT to maintain, Fuqua said. As a
result, the decks are being removed from the overpasses.
Steel and bearings that need repair are being fixed, and contractors
are then forming up and pouring concrete atop the steel.
In removing the bridge decks, the existing concrete was broken
and the pieces removed. That broken concrete will be reused
in future jobs.
Fuqua acknowledged that completely rebuilding the bridge decks
is hard work but added that IDOT assigned experts to the job.
"Actually doing it on I-57 under these conditions is
easier than closing like half a bridge deck and repouring
it," he said. "That way would take twice as long;
we'd be out there four years instead of two years."
IDOT issued press releases, published and distributed brochures
and met with community leaders to help get the word out to
the public that traffic would be reduced to two lanes and
running slower than normal. "Eventually people learned
they needed to slow down in the work zone and they could make
it through without any difficulty," Fuqua said.
Noting the problems with the SMA on polished concrete last
summer, Fuqua said things are better this year. "It seems
like the job is going smoother this year, and I'm quite pleased
with it," he added. "We're doing $80 million of
work in just two years, without too much congestion."
|