Features - August 2003

No Little Plans Made for Lake Shore Drive Rebuild

Traffic flow, pedestrian access enhanced and park protected during redo of drive's southern portion
Like a torch through the generations, Daniel Burnham's vision for Chicago helped guide the $162 million reconstruction of South Lake Shore Drive. Full Story >>


Top Specialty Contractors' Billings Total $4 Billion

Revenues down, fears up in low-gear economy
The annual Midwest Construction survey of specialty contractors in Illinois, Indiana and Wisconsin found billings for the top-150 firms in the tri-state region last year were $4 billion. Full Story >>


New Year, New Pavement

Stone matrix asphalt used creatively on $80 million Interstate 57 project
When workers resurfaced the southbound lanes of Interstate 57 last summer, they discovered that the stone matrix asphalt they put down on the road had unusual characteristics. Full Story >>


Moving Heaven and Earth to Widen U.S. 151

Safety upgrades sought for Wisconsin highway
When construction team members working on one of the stretches of the $130 million U.S. Highway 151 widening project got a look at the soil under the proposed roadway, they did not like what they saw. Full Story >>


Above-Ground Planning Augurs Calumet Tunnel's Progress

Shafts and tunnels near surface, deep in limestone make up last leg of 'Deep Tunnel'
It took plenty of coordination among multiple entities to get work started on the $168.7 million Little Calumet Leg, the last passageway in Cook County's 109.4-mi.-long Deep Tunnel system. Full Story >>


Upgrades to Pump Up Water Plant's Capacity

Treatment process at Indiana facility maintained throughout project
Getting pumped has been important during the $56.9 million upgrade of the wastewater treatment plant in Lafayette, Ind. Full Story >>