|
Sitework Obstacles Give Workout to
Sports Center Crews
230-ft.-long roof panels
cover roof of Marquette University's Al McGuire Center
by Elaine Schmidt
From excavation to roofing, the $31 million Al McGuire Center
on Milwaukee's Marquette University campus has demanded creative
design and construction solutions.
Construction began July 1 on the 117,400-sq.-ft. facility
that will house a 4,000-seat arena for women's basketball
and volleyball games and men's basketball practice. There
also will be training and weight rooms and a sports medicine
component.
The arena is named for the coach that took the university's
men's basketball team, previously known as the Warriors, to
a national championship in the 1977 National Collegiate Athletic
Association tournament. The facility will open for basketball
practice on Oct. 1, with final completion slated for the following
January.
Underground Surprises
A host of complications on the L-shaped site, which shares
a city block with Cobeen Residence Hall, influenced design
and construction decisions.
"On the surface the site looked good," said Aleisha
Palaniuk, associate project manager for Opus North of Milwaukee,
the design-builder on the project. "We knew that there
were at least two tanks filled with low-level petroleum from
row houses and a gas station that used to be there.
"As we were digging, we hit 12 or 13 more tanks,"
she said. The tanks were drained, but some had leaked. The
contaminated soil was removed.
"For awhile we had barrels all over the site and the
smell was just atrocious."
Even uncontaminated areas of the excavation presented obstacles.
"There was a lot of rubble from the old row houses because
they used to just demo the buildings back into the hole,"
Palaniuk said. "On the south side we had to protect a
Marquette duct package that runs through the alley and a gas
main that runs directly into Cobeen."
The gas main had to be excavated, shut down and altered to
serve the new site as well as the dorm.
"We found out that there was a fiber optic line below
the sidewalk on the north side of the site," she said.
"We could locate it on the east and west end of the site,
but didn't know what happened to it in the middle. We were
told this connected to the banks and some of the buildings
downtown."
Crews had to resort to hand excavation, gingerly searching
for the fiber-optic line.
Keeping Neighbors Happy
Minimizing disruptions to Cobeen Hall and the city streets
surrounding the site was essential.
"We put a cantilevered foundation wall on that whole
north length, so we could excavate down, build the wall and
backfill right away instead of bracing on top," said
Dave Pettit, project engineer with Opus Architects and Engineers
Inc. in Minneapolis, the architect of record. "We didn't
want a hole open for several months where we would worry about
the street falling in."
Palaniuk said a system of wood lagging and piles on the north
side of the site was used, "where we are just a foot
off the property line because you can leave it in place."
She said that during excavation, Cobeen Hall began taking
on a significant amount of water, and Opus had to waterproof
the entire side of the exposed residence hall foundation.
The University decided that Cobeen's exposed foundation presented
the perfect time to remove an old boiler, which meant that
Opus had to tear into the building's exposed foundation while
maintaining structural stability.
Adapting Design to Site
Removing oil tanks, contaminated soil and row-house rubble
necessitated a 16-ft.-deep excavation on the north end of
the site, where the arena was to be located.
"Our first design did not push the bowl of the arena
into the ground," said Kent Davidson, director-architecture
for Opus Architects and Engineers.
"But we were confronted with below-grade issues that
meant we either needed to depress the structure into the dirt
or haul in engineered fill, which had a lot of negative construction
cost issues associated with it."
He said Opus worked with NBBJ Sports Facilities, the project's
Marina del Rey, Calif.-based design architect, and the university
to study ways to sink the bowl and fit the structure into
the campus architecture and surroundings.
"One of the benefits of sinking the bowl is that you
are able to come into the facility at concourse level,"
said Chuck O'Connell, architectural coordinator for Opus Architects
and Engineers. "You don't have to ramp up to get to the
seats." The lower profile of the sunken bowl also preserved
views from Cobeen Hall.
"When we pressed the facility into the ground, it allowed
the weighttraining area, locker rooms and other areas that
didn't have a lot of daylight to be built in a more efficient
and compact way and kept the footprint at a manageable level,"
Davidson said.
Chicken or Egg
As the project came out of the ground, careful planning and
coordination were required to maintain structural stability
as precast concrete panels, some of them 52 ft. long, were
set in place and shoring was removed.
"We had to have the steel structure of the roof diaphragms
in place before we could take the shoring off the precast,"
Pettit said. "This is typical. It is done in warehouse
construction all the time.
"But it is easier when you have access to both sides
of the precast. With Cobeen Hall less than 10 ft. away, we
could only shore into the new structure. We had to leave out
portions of the main concourse floor because we couldn't pour
the level-one slab until we had the shoring out. We couldn't
take the shoring out until we had the roof in place."
He called it a "chicken and the egg scenario,"
explaining that they had to work with all the subs so that
everyone knew what could come out and what could go in at
any given moment.
Lifting Long Loads
With Cobeen Hall less than 10 ft. away from the southern
wall of the arena, lifting precast panels into place required
detailed safety plans.
"We had to have an evacuation plan in Cobeen,"
Palaniuk said. "We made sure no one was in the rooms
adjacent to where we were working." These lifts had to
be planned well in advance so that the University could make
arrangements with students ahead of time.
Lifting roof joists into place in the tight quarters also
required careful planning.
"The original design called for three major steel trusses
that would span the arena," said O'Connell. "We
were pretty far along in that design, to the point of looking
at how it would be staged and erected, when we came up with
an alternative design of long-span joists.
"It gave us the same structural support, was less expensive
and was much more conducive to the staging of construction."
Davidson said the result is a simple, elegant structure.
In fact, looking up at the joists from the concourse level
or the arena floor, the effect is one of filigree, rather
than heavy trusses.
The joists may look light, but installation was tricky. Davidson
said the 23 joists, which span 156 ft., 6 in., were delivered
in two pieces. They were bolted together on the arena floor
and hoisted into place.
The lifts required evacuation of all areas beneath and adjacent
to them. Lifts could only occur in optimal wind conditions.
Topping it Off
"The most interesting part of the arena is the roof,"
Pettit said. In addition to the long-span joists that are
visible inside the arena, the standing-seam, steel roof is
a distinctive architectural feature.
O'Connell said the material choice "expressed the geometry
of the barrel roof better than anything else."
Installing the 230-ft.-long continuous panels of roofing
steel required careful staging and a lot of manpower.
"We have done many projects, but at 230 ft., this is
the longest one to date," said David Wiess, general manager
of Specialty Associates Inc. of West Allis, Wis.
The panels are run onsite in a process O'Connell described
as a combination of rolling and pressing.
Crews pressed the panels on the flat roof of the McGuire
Center's administration building, walking them from that lower
roof to the barrel roof via a crane-built scaffold.
"Ten guys walked the panels up the scaffold rigging
onto the barrel roof and set them there," Wiess said.
Starting on the north end, with a worker positioned about
every 20 ft. along the length of the panel, crews would pick
up one panel and set it in place, clipping it on 4-ft. centers.
Wiess added that two mechanical seamers are clamped on at
the roof's high point. As they seam, they roll gravity down
the arch of the roof to workers waiting at the roof line to
receive them.
The seamers, which overlap to create a seal at the center
point of the roof, run about 30 ft. per minute, covering 60
ft. per minute when two seamers are running in opposite directions.
In addition to being impervious to water, the parallel ribs
of the standing-seam steel add graceful lines over the arch
of the barrel roof.
|